Bathroom remodel

Bathroom Remodel by Building Brothers, Inc. (53486 bytes)

March 3, 2001

Before photos

March 8, 2001

Demolition begins

March 9, 2001

Demolition Continues

March 16, 2001

Plumbing begins - one piece tub installed

March 21, 2001

Rough electrical is installed

March 26, 2001

Insulation is installed

March 28, 2001

Acrylic block and T111 installed

March 29,2001

Blue board installed

April 3-4, 2001

Taping is done

April 9, 2001

Primer and paint applied

April 10, 2001

Door, trim and linoleum installed

April 11, 2001

Sink, toilet, odds and ends

April 12, 2001

Heater/exhaust fan/lights and wall switches installed

April 17, 2001

Washer/dryer connected

June 26, 2001

Cabinet and mirror installed....project completed.